We deliver fire protection, power distribution and complete civil and MEP works on generation, refinery and infrastructure projects across Saudi Arabia.
On a generation plant or a refinery the fuel, the plant and the cost of an outage all raise what the systems have to do. A sprinkler layout that would pass in a commercial building will not survive review here.
These clients also judge a contractor on documentation and predictability as much as on installation. The calculation has to hold up, and the records have to be there when the authority asks.
Green Flash Engineering and Contracting delivers fire protection and electrical infrastructure on power generation and refinery projects in Saudi Arabia, including the Rabigh 2 Mourjan IPP expansion and the SAMREF refinery at Yanbu. Power distribution on projects of this type runs through electrical substations, transformers and MV switchgear.
Fire protection systems designed to the hazard classification, with hydraulics built on the water supply that is actually available.
High and low voltage underground distribution, tested and recorded before backfill.
Where the scope calls for it we take structure and services together, so the openings and builder’s work the services depend on sit with the same contractor.
Addressable detection interfaced to the mechanical and suppression systems, proven at commissioning against a written matrix.
Occupancy and hazard classification set the design density and the area of operation. Everything downstream follows from getting that right.
Hydraulic calculations use the site’s actual water supply, not an assumed figure that fails at witness testing.
Pipework is hydrostatically tested section by section and cable routes proven before cover, with results recorded progressively.
Pump curves verified, flow tests witnessed, cause and effect proven, and the system taken through to Civil Defence sign off.
We supplied and installed the fire protection system for the Rabigh 2 Mourjan IPP power generation plant expansion, and delivered complete civil and MEP works on two refinery buildings in Yanbu for main contractor SAS Systems Engineering.
We also installed underground power cables at Amaala on the Red Sea, and at an aircraft component factory in Jeddah.
Yes. We supplied and installed the fire protection system on the Rabigh 2 Mourjan IPP expansion in 2026.
Yes. Complete civil and MEP works on two buildings at a refinery in Yanbu, delivered for the main contractor across 2025 and 2026.
Yes, and regularly. We are comfortable working inside another contractor’s programme and reporting into their site management.
We do. Drawings, hydraulic calculations, the submission, the comments and the follow through to approval.
Send the layout, the hazard and the water supply, or just the type of plant and where it is. We will come back with how we would run it.